The Cement mortar that is prepared in 1: 3 proportions using standard sand (as per IS:650) and tested at standard laboratory conditions and should gain the compressive strength of not less than 33 MPa after 28 days,
| DESCRIPTION | IS REQUIREMENT | PARASAKTI RESULTS |
|---|---|---|
| 3 Days (72 ± 1hour) | Not less than 16 MPa | 22-25 MPa |
| 7 Days (168± 2 hour) | Not less than 22 MPa | 33-36 MPa |
| 28 days (672±4 hour) | Not less than 33 MPa | 52-55 MPa |
| DESCRIPTION | IS REQUIREMENT | PARASAKTI RESULTS |
|---|---|---|
| Initial Setting time | Not less than 30 Minutes | 130-160 Minutes |
| Final Setting time | Not more than 600 Minutes | 230-260 Minutes |
| DESCRIPTION | IS REQUIREMENT | PARASAKTI RESULTS |
|---|---|---|
| By Blaine method | Not less than 300 M2/Kg | 330-350 M2/Kg |
| DESCRIPTION | IS REQUIREMENT | PARASAKTI RESULTS |
|---|---|---|
| Le-Chatlier method | Not more than 10mm | 1-2 mm |
| Autoclave method | Not more than 0.80 percent | 0.02 - 0.15 % |
| Drying Shrinkage | Not more than 0.015 percent | 0.10% |
Applications
Used for Hydraulic Structures, Mass concrete structures like Dams, Bridge piers and thick foundation, Marine structures, Sewers and Sewage disposal works etc.